You have searched for -tamil-nadu in Awarded Tender Result. Click on any tender to view further details.
3211Widening and Improvements, Improvements, Rebuilding, Widening of culverts, Construction of Drain, Construction of load bearing drain and including Up Keeping for a period of 60 Months on Government Roads in Madathukulam (Highways), C&M, Sub Division. Package No.62 Road A :- Widening from three lane to four lane and rebuilding of Udumalpet - Dharapuram road at km 0/0 - 0/373 & 0/414 - 0/500 (SH 97) including upkeeping for a period of 60 months
Road B :- Widening from three lane to four lane and rebuilding of Udumalpet - Dharapuram road at km 0/500-1/0 (SH 97) including widening of culvert at km 0/6 including upkeeping for a period of 60 months
Road C :- Widening from three lane to four lane and improvements of Udumalpet - Dharapuram road at km 1/2 - 2/0 (SH 97) including upkeeping for a period of 60 months
Road D :- Construction of Drain at km 0/0 - 0/248 (LS) & 1/080 - 1/580 (RS) of Udumalpet - Dharapuram road including construction of load bearing drain at km 0/2 (LS) , Km 1/2 (RS) & 1/6 (RS) (SH 97)
Road E :- Improvements to km 0/0 - 1/0 of Udumalpet - Elayamuthur road including upkeeping for a period of 60 months"
TRN :
716234
|
Tirupur - Tamil Nadu
Contract Value :
6.09 Crore |Agency Name :
Highway Department
3212Widening, Improvements to Government Roads including Junction Improvements, Construction of CD works, Drain and Retaining wall and Up keeping for a period of 60 months in Edappady (H) C&M Sub Division (Package-22)
The Following works are involved in this package
1. Improvements of Edappady - Poolampatty - Mettur road at km 10/8-12/0 including widening of curves with junction improvements in the Town and Providing hard shoulders (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0375)
2.Widening from Intermediate lane to Two lane and Improvements of Edappady - Poolampatty - Mettur road at km 12/0-12/935 including construction of CD works and storm water drain (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0359)
3.Construction of drain at km 10/8-11/430 & 11/6-12/0 of Edappady - Poolampatty - Mettur road including Retaining wall and CD works (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0392)
4.Construction of Retaining wall at km 12/0-12/935 of Edappady - Poolampatty - Mettur road (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0393)
5.Junction Improvements at km 6/8 including construction of drain from km 6/6-6/8 of Chittur - Poolampatti Road Including Upkeeping for a period of 60 months (01-CRIDP-19-20-O-2629) "
TRN :
720174
|
Salem - Tamil Nadu
Contract Value :
6.80 Crore |Agency Name :
Highway Department
3213Widening and Improvements, Improvements to Riding Quality, Reconstruction of Box Culverts, Construction of Retaining Walls and including Up Keeping for a period of 60 Months on Government Roads in Palladam (Highways), C&M, Sub Division. Package No.46
A) Widening from Two lane to Three lane and Improvements of Palladam - Cochin Frontier road at Km 2/0 - 3/0 (SH 163) including upkeeping for a period of 60 months
B) Widening from Two lane to Three lane and Improvements of Palladam - Cochin Frontier road at Km 3/0 - 3/350 and 3/650 - 4/0 (SH 163) including upkeeping for a period of 60 months
C) Widening from Two lane to Three lane and Rebuilding of Palladam - Cochin Frontier road at Km 3/350 - 3/650 including construction of retaining wall at Km 3/350 - 3/650 (SH 163) including upkeeping for a period of 60 months
D) Reconstruction of Box culvert Single cell of size 1m x 1m at Km 0/8 and 1/10 of Karanampettai- Rasagoundempalayam road
E) Improvements to Riding Quality at Km 0/0 - 1/8 of Karanampettai - Rasagoudempalayam road including upkeeping for a period of 60 months
F) Improvements to Riding Quality at Km 1/8 -3/0 of Karanampettai- Rasagoudempalayam road including upkeeping for a period of 60 months
G) Improvements to Riding Quality at Km 3/0 - 4/190 of Karanampettai- Rasagoudempalayam road including upkeeping for a period of 60 months
H) Improvements to Riding Quality at Km 4/6 - 7/0 of Kallipalayam - Vavipalayam road including upkeeping for a period of 60 months
I) Improvements to Riding Quality at km 0/0 - 2/0 of Valaiyapalayam road Km 7/6 of road from Palladam - Dharapuram road to Km 2/2 of Pongalur road to Valayapalayam road including upkeeping for a period of 60 months"
TRN :
704979
|
Tirupur - Tamil Nadu
Contract Value :
6.16 Crore |Agency Name :
Highway Department
3214Improvements to Riding Quality to Government Roads including Construction and Reconstruction of Box Culvert,Drain and Up keeping for a period of 60 months in Edappady (H) C&M Sub Division (Package-23)
The Following works are involved in this package
1.Construction of Drain at km 8/0-8/4 of Magudanchavadi - Komarapalayam road (via) Edappady including CD works(SH 221) (01-CRIDP-19-20-S-0389)
2. Improvements to Riding Quality at km 18/8 -19/2 and 19/4 - 20/0 of Magudanchavadi -Komarapalayam road (via) Edappady (SH 221)including Upkeeping for a period of 60 months (01-CRIDP-19-20-I-4521)
3. Improvements to Riding Quality at km 20/0 -22/2 of Magudanchavadi - Komarapalayam road(via) Edappady (SH 221) including Upkeeping for a period of 60 months (01-CRIDP-19-20-I-4522)
4. Raising the dip at km 19/4 of Magudanchavadi -Komarapalayam road (via) Edappady including Construction of Box culvert (SH 221) including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0386)
5. Improvements of Magudanchavadi - Komarapalayam road (via) Edappady at km 14/2- 15/2 & 16/4-16/6 including easing the approaches at Km 14/8 & 14/10 (SH 221) including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0380)
6. Improvements of Magudanchavadi - Komarapalayam road (via) Edappady at km 16/6 - 17/8 including easing the Edappady Bus stand approaches(SH 221) including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0381)
7. Improvements to Riding Quality at km 12/2 - 14/2 of Magudanchavadi - Komarapalayam road (via) Edappady (SH 221) including Upkeeping for a period of 60 months(01-CRIDP-19-20-I-4530)
8. Reconstruction of Box culvert at km 13/2 of Magudanchavadi - Komarapalayam road (via) Edappady (SH 221) including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0398)"
TRN :
719183
|
Salem - Tamil Nadu
Contract Value :
6.56 Crore |Agency Name :
Highway Department
3215Improvements to Riding Quality, and including Up Keeping for a period of 60 Months on Government Roads in Dharapuram & Mulanur (Highways), C&M, Sub Division. Package No.66 Road A :- Improvements to Riding quality at km 1/0 -3/4 & 4/4 -4/8 of Dharapuram - Poolavadi road (MD 884) including upkeeping for a period of 60 months
Road B :- Improvements to Riding quality at km 1/0 -3/8 of Suriyanallur - Velappampalayam road including upkeeping for a period of 60 months.
Road C :- Improvements to Riding quality at km 4/8 - 8/2 of The road from Kallipalayam to join at km 20/8 of Dharapuram - Pollachi, including upkeeping for a period of 60 months
Road D :- Improvements to Riding quality at km2/4 - 4/0 & 5/0 - 6/2 of Kundadam - Ponnapuram road including upkeeping for a period of 60 months
Road E :- Improvements to Riding Quality at Km 0/0-2/0 of Malamedu - Velampoondi road including upkeeping for a period of 60 months
Road F :- Improvements to Riding Quality at Km 7/0-11/0 of Akkaraipalayam - Karaiyur road (MD 989) including upkeeping for a period of 60 months
Road G :- Improvements to Riding Quality at Km 0/0-2/6 of Karur - Dharapuram road to Salaripatty road including upkeeping for a period of 60 months
Road H :- Improvements to Riding Quality at Km 0/0-5/4 of Salakkadai - Eulugamvalasu road including upkeeping for a period of 60 months
Road I :- Improvements to Riding Quality at Km 9/0-12/6 of The road branching at Km 53/8 of Udumalpet - Chinnadharapuram road to District limit road (via) Chinnakkampatty, Ponnivady including upkeeping for a period of 60 months
TRN :
716235
|
Tirupur - Tamil Nadu
Contract Value :
5.53 Crore |Agency Name :
Highway Department
3216Improvements and Improvements to Riding Quality to Government Roads including Construction of Drain, Retaining Wall, Box Culvert and up keeping the roads for a period of 60 months in Salem C&M Sub Division (Package-3)
The Following works are involved in this package
1.Improvements of Omalur Main road in Salem at km 0/0 - 1/2 (SH 218) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0340). 2,Improvements of Varanasi - Kanyakumari Road (Abandoned NH7) at km 204/0 - 204/8 (SH 80) including upkeeping for a period of 60 months.
(01-CRIDP-19-20-S-0341).
3,Improvements of Varanasi - Kanyakumari Road (Abandoned NH7) at km 203/4 - 204/0 including Construction of Drain at Km.203/4-203/10 of Varanasi Kanyakumari road (Abandoned NH-7)(SH 80) including upkeeping for a period of 60 months (01-CRIDP-19-20-S-0342). 4,Improvements to Riding Quality at km 2/0 - 3/4 and 5/6 - 6/0 of Shevapet-Elampillai Road (MD 421) including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4468).
5,Improvements to Riding Quality at km 0/0 - 0/8, 1/6 - 2/4, 3/6 - 5/2 and 7/8 - 8/279 of Suramangalam - Sivathapuram - Neikarapatty road including upkeeping for a period of 60 months (01-CRIDP-19-20-I-4505). 6,Improvements of Pension line road at km 0/0 - 0/930 including construction of Box culvert , Drain and Retaining wall(MD 655) including upkeeping for a period of 60 months (01-CRIDP-19-20-M-1305)."
TRN :
720165
|
Salem - Tamil Nadu
Contract Value :
7.48 Crore |Agency Name :
Highway Department
3217Widening and Improvements, Construction of Drains and Widening of culverts on Governement Roads in Tirupur North (Highways), C&M, Sub Division. (Package No - 33) Road A :- Widening from Two lane to Three lane and Improvements of Tirupur - Somanur road at km 5/8 - 6/100 and 6/550 - 7/0, Improvements at km 6/100 - 6/550 (SH 169) including upkeeping for a period of 60 months
Road B :- Widening from Two lane to Three lane and Improvements of Tirupur - Somanur road at km 7/0 - 8/0 incuding Construction of Box Culvert at Km 7/2 (SH 169) including upkeeping for a period of 60 months
Road C :- Widening from Two lane to Three lane and Improvements of Tirupur - Somanur road at km 8/0 - 8/6, Improvements at km 8/6 - 8/8 and 8/850 - 9/0 incuding Construction of Box Culvert at Km 8/2 (SH 169) including upkeeping for a period of 60 months
Road D :- Widening from Two lane to Three lane and Improvements of Tirupur - Somanur road at km 4/2 - 4/700 (SH 169) including upkeeping for a period of 60 months
Road E :- Widening from Single lane to Intermediate lane and Improvements of Tirupur - Vijayamangalam road at Km 4/8 of Parapalayam at km 0/0 - 1/0, Improvements at km 1/0 - 2/2 including construction of retaining wall at Km 1/6,1/8 & 1/10 and Construction of RCC Drain at Km 0/2 including upkeeping for a period of 60 months
Road F :- Improvements to Riding Quality at km 5/2 - 6/0 of Tiruppur - Vijayamangalam road (SH 19 A) including upkeeping for a period of 60 months
Road G :- Improvements to Riding Quality at km 6/0 - 6/300, 10/550 - 10/665 and 11/180 - 11/350 of Tiruppur - Vijayamangalam road (SH 19 A)including upkeeping for a period of 60 months"
TRN :
704952
|
Tirupur - Tamil Nadu
Contract Value :
6.98 Crore |Agency Name :
Highway Department
3218Widening, Improvements to Government Roads including Junction Improvements, Construction of CD works, Drain and Retaining wall and Up keeping for a period of 60 months in Edappady (H) C&M Sub Division (Package-22)
The Following works are involved in this package
1. Improvements of Edappady - Poolampatty - Mettur road at km 10/8-12/0 including widening of curves with junction improvements in the Town and Providing hard shoulders (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0375)
2.Widening from Intermediate lane to Two lane and Improvements of Edappady - Poolampatty - Mettur road at km 12/0-12/935 including construction of CD works and storm water drain (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0359)
3.Construction of drain at km 10/8-11/430 & 11/6-12/0 of Edappady - Poolampatty - Mettur road including Retaining wall and CD works (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0392)
4.Construction of Retaining wall at km 12/0-12/935 of Edappady - Poolampatty - Mettur road (SH 220A) Including Upkeeping for a period of 60 months (01-CRIDP-19-20-S-0393)
5.Junction Improvements at km 6/8 including construction of drain from km 6/6-6/8 of Chittur - Poolampatti Road Including Upkeeping for a period of 60 months (01-CRIDP-19-20-O-2629) "
TRN :
719184
|
Salem - Tamil Nadu
Contract Value :
6.80 Crore |Agency Name :
Highway Department
3219Widening and Improvements, Improvements to Riding Quality, Widening the Curve, Construction of Box Culverts, Construction of Retaining Walls, Reconstruction of culverts, Widening of RCC slab culverts, and including Up Keeping for a period of 60 Months on Government Roads in Udumalpet (Highways), C&M, Sub Division. Package No.61 Road A :- Widening from Intermediate lane to Two lane and Improvements of km 15/6 of Udumalpet-Chinnar road - Amaravathi nagar road km 15/6 at km 2/4 - 4/0 (MD 167) including up keeping for a period of 60 months.
Road B :- Improvements of Riding Quality at km 5/0 - 5/2 and 7/8 - 12/0 of Udumalpet - Chinnar road (MD 509) including up keeping for a period of 60 months.
Road C :- Widening the curve at km 10/2 of Udumalpet - Chinnar road and including Construction of Retaining wall at km 10/2 (MD 509)
Road D :- Widening from Single lane to Intermediate lane and Improvements of Periyapatti - Negamam road (via) Ammapatti at km 12/0 - 13/6 and including Reconstruction of culvert at km 12/2 &12/6 including up keeping for a period of 60 months.
Road E :- Widening from Single lane to Intermediate lane and Improvements of Periyapatti - Negamam road (via) Amanthakadavu at km 8/3 - 9/0 including up keeping for a period of 60 months.
Road F :- Improvements to Riding Quality at km 0/0 - 3/0 of The road branching at km 5/6 of Udumalpet-Senjerihills road to Pottayampalayam including up keeping for a period of 60 months.
Road G :- Construction of box culvert at km 0/8 & 2/2 of Negamam-Erisanampatti road branching at Km 26/8 of Anaimalai - Poolankinar road (Via) Vilamarathupatti.
Road H :- Widening RCC Slab Culvert across PAP canal at km 0/10 of The road branching at km 5/6 of Udumalpet-Senjerihills road to Pottayampalayam and Construction of retaining wall at km 2/6 & 2/8"
TRN :
716236
|
Tirupur - Tamil Nadu
Contract Value :
5.92 Crore |Agency Name :
Highway Department
3220Special Repairs to Government Roads in Valapady (H) C&M Sub Division (Package 79)
The Following works are involved in this package
1. Special Repairs to Salem-Ulundurpet road to Vadugathampatty road (via) Chinnakrishnapuram Km 0/0-1/0.
2. Special Repairs to Salem-Ulundurpet road to Vadugathampatty road (via) Chinnakrishnapuram Km 1/0-2/4.
3. Special Repairs to Km 2/0-3/0 Mangalapuram-Veppilaipatty road .
4. Special Repairs to Km 38/0-39/0 Ayothiayapattinam - Belur - Kilakkadu road .
5. Special Repairs to Km 3/0-4/070 Mangalapuram-Veppilaipatty road .
6. Special Repairs to Km 0/0-2/0 Thandanur Diversion road.
7. Special Repairs to Km 39/0-39/5 Ayothiayapattinam - Belur - Kilakkadu road .
"
TRN :
720113
|
Salem - Tamil Nadu
Contract Value :
1.51 Crore |Agency Name :
Highway Department