Liasoning Service

561399

Liasoning Service

Warm Greetings from www.thetenders.com, the fastest growing tender information portal in India.

Supply Of Technical And General Specification, L 1 Station, Name Of Work: Start Up Bypass Station Spray Nozzles Inspection Work. Period O F Work: During Total Shutdown Of L Station Phase-1 2021-2022 Tentative Start Date 15.01.2022 Inspectin With In 2 Days Valve Drawi Ng Attached. Scope Of Work: ##Contractor Shall Visit The Site, Review The Drawings, And Make Himself Fully Aware With The Scope, P Lant Access, Facilities, Work Duration, Shutdown Schedules, Facilities, Complexities, Safety Measures Etc., Before Submitting The Qu Otation. ##Conduct Site Survey And Safety Inspection For Suitability To Execute The Work. ##Mobilize The Team, Equipment, Tools, Etc . ##Identification Of The Spray Nozzles. ##Removal Of The Of Spray Nozzles. ##Clean And Inspect For Any Defect. If Any Defect Is T Here Inform Dewa Engineer. ##Replace The Spray Nozzles. ##Total No Of Nozzles For Startup By Pass 9Nos. ##Replace The Gaskets And Reinstall The Nozzles Back. ##Housekeeping The Area. ##Invoice Amount Will Be According To Actual Work Done. ##A Safety Meeting Will Be Held To Evaluate The Risk Involved In Methods To Be Used. ##Risk Assessment And Tool Box Talk To Be Given To The Employees. ##In Spection And Approval From Dewa Personnel. ##De-Mobilization And Site Clearance. ##The Contractor Is Responsible For All Waste Mater Ial Segregation And To Keep In The Safe Location Assigned. ##Work To Be Carried Out During Total Shut Down Overhaul Period, I.E. 15/ 01/2022 To 26/01/2022 Work To Be Completed Within 2 Days. The Contractor Shall Beresponsible For Any Delay In Carrying Out The Work . 1.#Dewa Scope Of Supply ##Ndt ##Scaffolding If Required ##Insulation Material If Required 2.#Warranty ·#A Minimum Warranty Of 12 Months For Weld Joints And Workmanship Shall Provide By The Contractor Starting From The Date Of Final Clearance From Dewa. ·# In Case Of Any Damage/Defect Of The Work Carried Out Under This Contract Within This Warranty Period, The Contractor Shall Attend An D Carry Out The Necessary Repair Work And Rectify The Defect Within Short Period Without Affecting The Production Of Electricity And Water. General Terms & Conditions Technical Safety During The Work: ·#Contractor Staff Must Have Valid Gate Pass Before Entering The Plant Premises. ·#Contractor Shallgive Daily Tool Box Talk, Risk Assessment And Dynamic Risk Assessment To Their Staffs. ·#Con Tractor Staff Involved In Any Activity Shall Confirm The Availability Of Line Clearance Lc And Permit To Work Ptw Before Start O F Any Work. ·#Contractor Staff Must Check And Verify Of The Isolations Before Starting Of Any Overhauling Work. ·#The Contractor Sha Ll Check The Condition Suitable To Carry Out The Work. Conduct Site Survey And Safety Inspection To Assess The Working Environment. ·#Contractor Shall Ensure Housekeeping Is Done On Daily Basis. ·#Contractor Site Supervisor Shall Be Continuously Present At The Wor K Site To Supervise The Job. ·#The Contractor Must Engage A Qualified Safety Officer To Ensure Observance Of Safety And Safe Workingpractices By His Men At Site At All Time. The Safety Supervisor Shall Keep All Records Tbt, Risk Assessment, Hot Work Permit, Ptw, Msds, All Safety Related Documents#. ·#Contractor Staff Involved In Any Activity Shall Use Appropriate Ppes Including Gloves, Helm Et, Goggles, Safety Shoe And Mask Etc. ·#Contractor Staff Shall Use Full Body Safety Harness When Working At Height. ·#Only Tested A Nd Certified Rigging Tools Shall Be Used During The Work. All The Rigging Tools Must Have Valid Test Certificates And It Must Be Pro Duce To Dewa Foreman/ Engineer Upon Request. ·#Contractor Must Be Ready With All Required Resources To Execute The Work As Per Agree D Scope Work During The Outage Schedule To Avoid Any Delay. ·#Daily Hot Work Permit Is Required Before Start Of Any Hot Work Like Welding/ Cutting/ Grinding/Drilling/Heating Etc. ·#During Welding / Cutting, Ensure That Welding Spark / Cutting Materials Shall Not F All On Nearby Equipment. Adequate Fire Blankets Shall Be Used During Welding And Cutting Work. ·#No Any Hot Work Shall Be Started Wi Thout Getting Hot Work Permit And Without Fire Extinguisher Near The Work Location. ·#Daily Confined Space Work Permit Is Required B Efore Start Of Any Work Inside Confined Space ·#Contractor Shall Ensure No Disturbance To The Nearby Operating Plant / Equipment. ·# Contractor Is Responsible For Any Damage Or Effect On Installed Or Operating Machines /Equipment/ Properties. ·#Ensure Proper Handli Ng Of Materials, Tools. Suitable Belts Are To Be Worn To Avoid Tools From Falling. ·#Safety Signs Shall Be Provided At Worksite And Wherever Required The Area Is To Be Barricaded For Safety And To Prevent Unauthorized Entry. ·#Contractor Staff Are Allowed To Work Only In The Authorized Work Place Designated By Dewa. ·#Contractor Staff Are Required To Wear Their Company Uniform & Carry Their G Ate Pass Ids During The Work Inside Dewa Premises. ·#All The Safety And Security Procedures Of Dewa Shall Be Strictly Adhered. ·#In Case Any Accident/Near Miss/ Abnormality, Shall Be Immediately Reported To Dewa Foreman/ Engineer. ·#The Contractor Must Engage A Ce Rtified & Experienced Rigger For All Lifting Activities ·#Contractor Shall Keep Valid Welder Certificate, Rigger Certificate, Weldin G Machine Certificate, Power Tools Testing Certificate At Site And Shall Be Produce Todewa Foreman/ Engineer Upon Request. ·#Contra Ctor Shall Keep The Msds For The Consumables Crc/ Wd 40 Etc. Used At Site. ·#All The Welding Matching Power Cables, Welding Cables, Power Cables Must Be Tested And Free From Joints. ·#Cutting Set And Flame Heating Set Must Be Equipped With Back Fire Arrester. ·# Contractor Staffs Should Not Use Expired Cutting Disc, Grinding Disc & Welding Electrodes ·#Contractor Supervisor Shall Inform Dewa Foreman/ Engineer/Operator Before Use Of Service Air And Service Water. ·#Contractor Staff Should Not Use Instrument Air As It Can C Ause Trip Of The Plant. ·#Contractor Staff Should Not Go To Desal Area Or Other Areas #. For Lunch / Sitting / Sleeping. ·#Contrac Tor Work Must Be Started Sharply At 07:30Am And Shall Be Continue Up The End Of The Day. ·#If Any Work Will Continue After 18:00 Cl Ock And During Off Days, Ensure That Night / Holiday Permit Must Be Available. The Holiday / Night Work Permit Must Be Applied One D Ay Prior To The Holiday Before 10:00 Am. ·#During Holidays Contractor Shall Ensure That All The Resources But Not Limited To Sub-Con Tractor Manpower, Tools, Consumables, Workshop Facility And Vehicles Are Available For The Smooth Execution Of The Work. ·#Contracto R Has To Commence The Work Round The Clock / Double Shift If Required To Complete The Job Within The Agreed Duration. Waste Segr Egation And Disposal Hazardous Waste Segregation And Disposal A.#Ensure That Everyone Who Might Be Exposed To Hazardous Wastes Isaware Of Their Potential Effects And What To Do With Them. Red Bags To Be Used For Only Hazardous Waste Collection And To Be Dispos Ed In Appropriate Bins. B.#Used Crc & Wd40/ Cans/Lubrication Cans Should Be Disposed Separately In The Appropriate Bin. C.#Used Insu Lation Material I.E. Rock Wool & Ceramic Wool To Be Collected In Red Bags And Tie Properly With Cable Tie, Bag Shall Not Be Torn. De Wa Will Arrange For The Disposal Through Khadamatech Request. D.#Oil Sludge, Old Firefighting Foam, Detergent Coolant, Solvent, Soot Material From Boiler, Magnetite Scales From Boiler Internal, Insulation Material, Silica Gel, Empty Paint Container, Empty Thinner Container, Empty Aerosol Cans Crc/Wd40 Cleaner, Fuel Oil Filter Element, Ng Filter Element, Oily Rags/Cloth, Broken Glasses, Refrac Tory, Adhesive /Glue, Epoxy, Waste Grease, Mixed Oil And Acidic Waste Water Shall Be Segregated Properly E.#If The Disposal Of Hazar Dous Waste Is Under Scope Of Contractor As Per Scope Of Work, Contractor Has To Arrange The Disposal As Per Dubai

GTN :22581570
Dubai - Dubai

GLOBAL Instructions for obtaining this information:
  1. If you are a registered member, please login in the members area with your user id and password.
  2. If you are not a registered member, then first register for the services.
  3. If you don’t want to register, but want to download only this project information, then fill in the form.
  4. Email id and mobile should be correct. www.thetenders.com will not be responsible for non receipt of the desired information at your end owing to wrong email id and mobile number.
  5. Upon filling this form follow the next instructions.
  6. You will receive the information and documents on the email id provided by you.
  7. In case of any query please call us on +91 92760 83333
GLOBAL - Liason

Why www.thetenders.com ?

  • Fastest growing tender information portal in India
  • User friendly tender web portal with multiple search criteria
  • Reliable and quick tender information services
  • Reduces time, cost and man power required for tender cycle
  • Tenders information across India and Globe
  • Tenders categoried in various groups
  • Team, sprawling over entire Geography, scans various tenders and uploads them on our portal
  • Comprehensive and Sophisticated software to search online tenders
  • Search features by Product Keywords, Industries, States & Regions, Price, Organisation & Sectors etc.
  • Choose categories as per your choice
  • Daily alerts on emails about tenders of your category
  • Non English Tenders translated into English
  • 24 x 6 customer support with E-tendering support
  • Scanned copies of tender documents
  • Tenders from Government, Semi Government, Corporate Sector, Private Sector, PSUs, NGOs, state, city and local bodies
  • Download available tender documents.
  • Technical support for online and offline tenders including e-bidding, e-auction etc.
  • No hidden Cost / No Additional Charges / Quick service activation
  • Bid Form collection support
  • Bid Form filling support
  • Bid Form submission support
  • Provide SEO benefit for you site*
  • Available upcoming projects and Market research journals absolutely free.
  • Free 5 page website designing and hosting *
  • Provides platform to advertise your products daily through emails and reach the customer inbox directly. *
  • Tenders from newspapers
  • Tenders from websites

Set Tender Alert

Activate daily alerts to know the tenders available of your work.

Get alerts

Bidding Support

Ask experts, how to fill bid forms, submit bids, participate in bids.

Get in touch

GeM Registration

Looking for GeM Registration? Get in touch with us and we will do the needful.

Registration

Digital Certificate

Get DSC for e-Tendering, e-Auction, e-bidding, Corporations / Associations / Others Tenders

Purchase now

Tender Awards

Want to know who's got the tender and are looking for subcontracting?

Connect now

Projects

Government and other private players, Real-time Updates of Project Information

Get info

International Tenders

We almost cover all the regions and countries across the world. Click to take your business to new heights.

Start now

Web Design

Get the Best Offers & Deals, expertise in developing static websites, dynamic websites and e-commerce.

Design now